Danvers: Upcoming Gas Main Work – Elm St, Holten St, Sylvan St Area

DANVERS – National Grid and their subcontractor, Mirra, will be finalizing connections of the new gas mains over the next two weeks. Due to the complexity of this work and its location at the intersection of Elm Street, Holten Street, and Sylvan Street, some work will occur overnight.

Work Schedule:

  • Day Shift (7AM–4PM) – Expect traffic restrictions and detours
  •  Night Shift (8PM–6AM) – Detours as necessary

Detailed Schedule:

  • 5/29 – Day + Night
  • 5/30 – Day
  • 5/31 – No Work
  • 6/1 – Night
  • 6/2 – Day
  • 6/3 – Day + Night
  • 6/4 – 6/6 – Day
  • 6/7 – No Work
  • 6/8 – Night
  • 6/9 – Day
  • 6/10 – Day + Night
  • 6/11 – 6/13 – Day

All work is weather dependent.

If you have any questions or concerns, please feel free to contact: Zachary Pereira Supervisor, Gas Construction – National Grid at 978-998-1826

Thank you for your patience and cooperation as this important work is completed.

Share This Post